SN |
COUNTY |
CONSTITUENCY |
WARD |
PROJECT NAME |
SCOPE/ACTIVITIES |
NO. OF PERSON TARGETED |
ALLOCATION-KSHS. |
FIRST -ALLOCATION |
FROM BOARDS OWN BUDGET |
1 |
Narok |
Transmara West |
Poroko |
Oloosenti borehole |
Drilling and equipping, civil work including; piplines, storage, draw off points |
1,000 |
6,000,000 |
3,000,000 |
Drilling completed on 5/2/2019. A yield of 2m3/hr achieved. Design for equipping and pipeline extensions completed. Tenders advertised on 9/4/19 , opened , evaluated and awarded on 20/5/2019. |
2 |
Kericho |
Aina Moi |
Kapsoit |
Kapsoit |
Borehole and extension of Litein Water Supply |
2,000 |
6,000,000 |
3,000,000 |
Tenders for drilling & test pumping opened on 17th May, 2019,evaluation is ongoing. |
3 |
Siaya |
Rarieda |
Asembo East |
Kitambo Borehole |
Drilling and equipping, civil work including ; piplines, storage, draw off points |
1,000 |
6,000,000 |
3,000,000 |
Borehole drilling and test pumping completed. Design for equipping and pipeline extensions completed. Works advertised on 9/4/19. Bids opened on 25th April, 2019,evaluated and awarded on 9th May, 2019. |
4 |
Siaya |
Ugunja |
Ugunja |
Raduodi Primary school |
Drilling and equipping, civil work including ; piplines, storage, draw off points |
600 |
6,000,000 |
3,000,000 |
Hydrogeological survey completed and works tendered and awarded on 16th April, 2019. |
5 |
Siaya |
Ugenya |
Noth Ugenya |
Lifunga borehole |
Drilling and equipping, civil work including; piplines, storage, draw off points |
1,000 |
7,000,000 |
3,500,000 |
Borehole drilling and test pumping completed. Design for equipping and pipeline extensions completed. Borehole equipping and pipeline extensions works tendered and awarded on 9th May, 2019. |
6 |
Bomet |
Chepalungu |
Kongasis |
Keriba water project |
Construction of iron removal plant |
600 |
3,000,000 |
1,500,000 |
Tender documents revised due to non responsive bids and tenders will be advertised on 28th May, 2019. |
7 |
Homabay |
Rangwe |
Kagan |
Borehole for Achego Mixed Secondary School |
Drilling and equipping, civil work , storage draw off points |
1,500 |
5,000,000 |
2,500,000 |
Hydro geological survey has indicated non productive acquifer within the school. Design for rehabilitation of an existing borehole within the project area to serve the school is in progress |
8 |
Homabay |
Homabay Central |
Homabay Central Ward |
Komune Pan |
Site clearing, excavation/earth moving, embankment rehabilitation, fencing, water point both for livestock and humans, pipelines |
2,000 |
8,000,000 |
4,000,000 |
Contract awarded and works in progress at 60%. Completion affected by ongoing rains |
9 |
Homabay |
Mbita |
Gembe |
Oseno dam |
Site clearing, excavation/earth moving, embankment rehabilitation, fencing, water point both for livestock and humans |
2,000 |
8,000,000 |
4,000,000 |
Contract awarded and works in progress at 95%. Completion affected by ongoing rains |
10 |
Nyamira |
North Mugirango |
Mekenene |
Riondoro |
Site clearing, excavation/desilting embankment rehabilitation, fencing, water point both for livestock and humans |
3,000 |
4,500,000 |
2,250,000 |
Tender for Pan Construction floated, bids opened on 23rd May, 2019, Evaluation ongoing |
11 |
Nyamira |
Borabu |
Esesi |
Raitigo dam |
Site clearing, excavation/earth moving, embankment rehabilitation, fencing, water point both for livestock and humans |
3,000 |
6,000,000 |
3,000,000 |
Tender for Pan Construction floated, bids opened on 23rd May, 2019, Evaluation ongoing |
12 |
Kisii |
NyaribariMasaba |
Kiamokama |
Borehole for Kiamokama Friends School Project |
Drilling and equipping, civil work including |
2,500 |
6,000,000 |
3,000,000 |
Borehole drilling and test pumping completed. Design for equipping and pipeline extensions ongoing |
13 |
Kisii |
Bomachoge Chache |
Sengera |
Borehole for Riamosorori Youth Group |
Drilling and equipping, civil work including piplines, storage, draw off points |
2,000 |
6,000,000 |
3,000,000 |
Tender for drilling and test pumping done but terminated due to Contractors inability to provide perfomance bond. Retendered and awarded on 20th May, 2019 |
14 |
Kisii |
Bonchari |
Riana |
Nyagema Primary School |
Drilling and equipping, civil work including piplines, storage, draw off points |
2,000 |
6,000,000 |
3,000,000 |
Tendering done for drilling and test pumping done and awarded. Contract signed on 14/05/19. Contractor mobilizing to site. |
15 |
Kericho |
Belgut |
Kaptuser |
Borborwet |
Drilling and equipping of boreholes |
2,000 |
3,500,000 |
3,500,000 |
Tender for drilling and test pumping awarded.Contract terminated for failure by the bidder to provide performance bond. Tenders readavertised and awarded on 20th May, 2019 |
16 |
Kericho |
Belgut |
Kabiaga |
Chebirirbei |
Drilling and equipping |
2,000 |
3,500,000 |
3,500,000 |
Borehole drilling and test pumping completed. Design for equipping and pipeline extensions ongoing |
17 |
Kisumu |
Kisumu West |
Nyahera |
Borehole for Bar Union Primary School |
Drilling and equipping, civil work including pipelines, storage and draw off points |
1,100 |
5,000,000 |
2,500,000 |
Hydrogeological survey completed. Tender for drilling and test pumping done and awarded. Contract signed on 14/05/19. Contractor mobilizing to site. |
18 |
Kisumu |
Seme |
East Seme |
Rodi Borehole Project |
Equipping and rehabilitation of borehole |
1,500 |
3,500,000 |
1,750,000 |
There is an existing borehole to be rehabilitated. Under design for rehabilitation |
19 |
Migori |
Rongo |
Kangeso |
Kangeso borehole Water Project |
Additional water connections and drop pipes to Kangeso Secondary & Kangeso Church |
1,100 |
5,000,000 |
2,500,000 |
under design |
20 |
Migori |
Kuria East |
Ntimaru East |
Rewankwe Pan |
Site clearing, excavation/earth moving, embankment rehabilitation, fencing, water point both for livestock and humans |
2,000 |
4,500,000 |
2,250,000 |
under design |
21 |
Kisumu |
Seme |
West Seme |
Ridore Sec School |
Drilling and equipping, civil work including pipelines, storage and draw off points |
2,500 |
6,700,000 |
3,350,000 |
Hydrogeological survey completed. Tender for drilling and test pumping done and award being finalized |
22 |
Migori |
Nyatike |
Macalda Kanyarwanda |
Buche |
Site clearing, excavation/earth moving, embankment construction, spillway, fencing water point both for livestock and humans |
2,000 |
5,000,000 |
2,500,000 |
Under design and tender documents preparation |
23 |
Nandi |
Tinderet |
Kamasian |
Tachasis Water Supply Project |
Pipeline rehabilitation and extension |
3,500 |
5,000,000 |
2,500,000 |
Tender for works not awarded due to high bids received.Pipes under procurement. |
24 |
Kericho |
Bureti |
Litein |
Water supply for AIC Litein Girls Sec School, town and institutions |
Water Supply from Spring Intake inluding pipeline, storage and draw off point. |
2,000 |
7,000,000 |
3,500,000 |
Tender for works awarded. Construction in progress at 50% |
25 |
Nyamira |
Borabu Bomachoge |
Nyabitunwa |
Water supply extension |
Completion of Riokindo, Nyabitunwa & Nyamesocho Water projects |
1,500 |
3,700,000 |
1,850,000 |
under design |
26 |
Kisii |
West Mugirango |
Nyakoiba |
Nyakoiba |
Drilling and equipping, civil work including pipelines, storage and draw off points |
1,500 |
5,500,000 |
2,750,000 |
Tender for drilling and test pumping done and awarded. Contract signed on 14/05/19. Contractor mobilizing to site. |
27 |
Nyamira |
Nyaribari Masaba borehole |
Ekemuga |
Drilling of Ekemuga borehole |
Drilling and equipping, civil work including pipelines, storage and draw off points |
1,500 |
6,000,000 |
3,000,000 |
Tender for drilling and test pumping done and awarded. Contract signed on 14/05/19. Contractor mobilizing to site. |
28 |
Nyamira |
North Mugirango |
North Mugirango |
Drilling one borehole Nyankono Pri. School |
Drilling and equipping one borehole |
2,000 |
6,000,000 |
3,000,000 |
Hydrological survey to be done |
29 |
Bomet |
Bomet |
Kiromwok |
Kiromwok Secondary school borehole |
Drilling and equipping, civil work including pipelines, storage and draw off points |
1,500 |
5,000,000 |
2,500,000 |
Tendering in progress with evaluation of tenders ongoing |
30 |
Nyamira |
Kitutu Masaba |
Gesima |
Nyabogoya borehole |
Drilling and equipping one borehole Nyabogoya |
1,500 |
6,000,000 |
3,000,000 |
Tenders advertised, evaluated, awarded and contract signed on 14th May, 2019. |
31 |
Bomet |
Bomet Central |
Bomet Central |
|
Drilling and equipping of boreholes |
1,500 |
7,000,000 |
3,500,000 |
Hydrological surveys to be done |
32 |
Narok |
Narok South |
Naroosura Maji Moto |
Oldebess Water Supply |
Drilling , equipping and civil works |
1,500 |
6,000,000 |
3,000,000 |
Hydrological survey to be done |
33 |
Kericho |
Kipkelion West |
Kapngetuny |
Kapngetuny Water Supply |
Pipeline extension, 10km |
3,000 |
5,000,000 |
2,500,000 |
survey and design in progress |
34 |
Kericho |
Kipkelion West |
Kipkelion |
Tuiyobei Water Project |
Intake, rising main, treatment works and distribution |
3,000 |
8,000,000 |
|
Under design |
35 |
Kisumu |
Kisumu West |
Nyando |
Drilling & equipping solar powered boreholes |
i) Olasi pri. Sch. ii) Aboge pri sch iii) Sabako Pri. Sch. iv) Awasi market v) Wanganga pri sch vi) Oren pri sch – Drilling, equipping and solar power installation |
3,000 |
12,500,000 |
|
Tendering for drilling and test pumping done and awarded. Oren and Awasi, Contract signed on 14/05/19, contractor mobilizing to site. Aboge and Sabako award being finalized |
36 |
Kisumu |
Seme |
Central Ward |
Seme Technical Institute |
Drilling and equipping, civil work including pipelines, storage and draw off points |
3,000 |
3,500,000 |
|
Tendering for drilling and test pumping opened and evaluated. Award bieng finalized |
37 |
Homabay |
Kasipul |
Central Kasipul |
Orimba water project |
Intake, rising main, |
3,000 |
8,000,000 |
|
Design completed. Tenders advertised, opened evaluated and award to be finalized |
38 |
Bomet |
Bomet East |
Kembu |
Kaporuso water project |
Intake, rising main, treatment works and distribution |
3,000 |
8,000,000 |
|
Design completed. Tenders advertised, opened evaluated and award to be finalized |